Goodooga Stormwater Drainage Improvements
Description
These works were part of the State Government’s Aboriginal Communities Development Program initiative upgrading critical infrastructure for remote indigenous communities.
This project delivered earthworks, concreting and concrete kerb construction as part of the stormwater drainage improvement program for the remote township of Goodooga, NSW.
Works
- Earthworks (including pipe/culvert select fill, pipe ordinary fill, pipe backfill, road pavement base, road pavement sub-base)
- Concrete kerb and gutter construction
- Sprayed bituminous surfacing
- Causeway construction
- Culvert and pipe driveway crossings
- Dish drain crossing
- Graded swales
Challenges
- Cooperative Contracting
- Environmental Management
- Subcontractor Management
- Quality Control
Our Management
The contract involved many small and large variations and modifications.
CivilTeam continually adjusted and adapted the approach to the task as the design requirements were modified by the Site Superintendent.
Value Adding
Detailed planning, careful client consultation, and methodical works staging were keys to completing this project on time and within budget.
“Throughout, a successful project with open communication lines, prompt issue and risk registration and cooperative relationship between all stakeholders. We would like to note that the contractor employed local indigenous labourers, which we believe had a positive impact for the community and their ownership towards the improved stormwater drainage.”
Anna Montag, Project Manager, Arup