Mindi and Braeside Substation and Track Sectioning
Description
This project was part of Queensland Rail’s programme to provide increased services for the coal industry in the central Queensland coal region. The purpose of the project was to enhance the capacity of the power station installed in the Goonyella System, to be able to support forecast traffic.
The scope of the project included earthworks, foundations and drainage for both the Mindi and Braeside sites. The works were located approx100 km west of Mackay, near Nebo.
Works
- Reinforced concrete foundations
- Stormwater and pollution drainage
- Earthworks (including excavation, formation construction and selected material zone)
- Construction of a sub-base layer
- Electrical pits and conduit
- Earthing and fencing
- Re-vegetation
Challenges
- Working in remote regions - difficult access and supply logistics
- Subcontractor Management
- Working within the rail corridor
Our Management
The team established a good working relationship with all project stakeholders. CivilTeam implemented a Project Management System specifically for subcontractor supply and day labour, in line with the client’s requirements. CivilTeam ensured all works were carried out in accordance with the safety requirements of working within a rail corridor.
Value Adding
CivilTeam prioritised an inclusive partnership approach with all stakeholders, which assisted in completing works one week ahead of the contract completion date.
The project was completed within budget and to the satisfaction of the client.