Project Channel & Bridge Protection Works, Central Highlands, QLD Location Central Highlands, QLD Client QLD Dept. of Local Government and Planning Contract Value $4.9m Construction Period July 2013 – Dec 2013 due to EOT’s from variations

Channel & Bridge Protection Works, QLD

Description

This project involved channel and bridge protection works for 12 bridges in the Rolleston/Springsure area. The scope of works involved earthworks preparation and installing scour protection including gabion baskets, mattresses and rock.

Works

Key elements in this project included:

  • Installation of reno- mattress and gabion baskets
  • Road channel repairs
  • Bridge abutment repairs

Challenges

  • Live Traffic
  • Subcontractor Management

Our Management

Detailed planning, practical and real-time solutions were key strategies for success throughout the duration of this project. CivilTeam had some design issues on the final bridge – Van Dyke. It was CivilTeam’s proactive management with the client and designers which resulted in a cost effective solution being found within the desired timeframe with minimal disruption to operations.

Value Adding

Excellent client relationships led to an invitation to price similar works on four additional bridges in the area as a variation to the project – Gladstone Slope Stabilisation, QLD, Project 62.