Project Queensland Rail—Goonyella, System Three Feeder Stations Location Near Sarina, north QLD Client TrackStar Alliance Contract Value $3.2m Construction Period April 2008 to October 2008

Goonyella, System Three Feeder Stations

Description

This project was part of Queensland Rail’s infrastructure redevelopment to increase the capacity of the Goonyella Rail System - Australia’s largest export coal rail network at that time.

This component of the project included three new feeder stations at Bolingbroke, Balook, and Black Mountain near Sarina, QLD.

The works in the contract included bulk earthworks, road works, drainage, conduit placement, earthing, and the construction of concrete foundations for switch rooms, transformers and retaining walls.

Works

  • Bulk earthworks
  • Roadworks
  • Drainage
  • Conduit placement and earthing
  • Concrete foundations for switchrooms, transformers and retaining walls
  • Electrical pits, electrical wiring grids

Challenges

  • Project fast-tracked—tight construction timeframes, delays in the access to site
  • Design issues—numerous design changes
  • Principal supplied material issues
  • Project Management

Our Management

This contract involved numerous variations due to constant design modifications by the main contractor. CivilTeam minimised construction delays by establishing regular communication with the client and adjusting the works program as needed. In this way we successfully completed the works on time.

Value Adding

All variations were completed within the projected time frame, minimising costs to the client.