Project Profile

Project Moree Waste Management Facility Location Moree, NSW Client Moree Plains Shire Council Contract Value $3.3m Construction Period December 2007 to July 2008

Moree Waste Management Facility

Description

This project delivered a new waste treatment facility for Moree Council. CivilTeam identified issues in the design and potential construction problems prior to arriving on site. This avoided numerous delays, variations and alterations on the project, which would have been very costly to the client.

Works

  • Bulk earthworks
  • Construction of HDPE and clay-lined waste disposal area and leachate pond
  • Construction of environmental earth mounds
  • Construction of a 20m deep pump station
  • Leachate drainage system
  • Construction of haul roads and drainage
  • Workshop and weighbridge buildings

Challenges

  • Remote location - limited scope for materials and equipment supply
  • Quality issues with client supplied poor quality base course
  • Lead times on materials supply
  • Environmental Management (endangered plant species Desmodium campylocaulon
  • Significant rain events
  • Drainage issues, resulted in significant ponding of water around road network
  • Failure of follow-on trades to adequately protect installed works

Our Management

By identifying issues early on, CivilTeam avoided numerous delays and reduced the scope for variations on the project.

The site team managed the remote location challenge by sourcing suppliers and verifying their conformance and ability to complete the works prior to arrival on site.

Value Adding

By utilising precast pipework to install a retro fitted sump pit 12m deep, the price of the variation was reduced, as was the EOT required to complete the process. The works were completed eight weeks ahead of schedule, including all variations.

Excellent client relationships led to further invitations to price future jobs, which resulted in repeat work for CivilTeam on the Moree Water Supply Desalination Project - Project 26.